The Duplex currently has six renters and is taking more applications - 6/21/2018
Completed
The Parking is In and carpet is next - May 22, 2018
The Inside is Ready for Carpet May 17, 2018
Sidewalk Installed and Parking Lot Ready for Asphalt - May 11, 2018
Landscape Prep almost Complete - May 8, 2018
Starting the parking and landscaping outside May 1, 2018
Cabinets are Going Up - April 27, 2018
Outside of House - April 20, 2018
Painting the Inside and Moving - 4/16/2018
Exterior Siding is completed 3/27/2018
The Duplex is Moving Fast 3/22/2018
Now It is Coming Together - March 13, 2018
Starting to take Shape - March 7, 2018
Starting to Look Like a Duplex -Feb 15, 2018
Really Coming Together - Feb 6, 2018
And Higher, February 2, 2018
Still Going Higher - Jan 29, 2018
2nd Floor - Jan 26, 2018
The Duplex is Going Up Fast - Jan 19, 2018
The First Floor Frame goes up - Jan 12, 2018
The First Floor is in place and the Basement is Framed - Jan 11, 2018
Basement nearing Framing Completion Dec 29, 2017
Floating Floor is completed and Framing Started, Dec 26, 2017
Floating Floor is being installed Dec 20, 2017
Duplex Basement November 21, 2017
Forms are Pulled Nov 13, 2017
Basement Formed and Poured Nov. 10, 2017
Grading Beams Poured October Nov. 3, 2017
Constructing Grade Beams - Oct 31, 2017
|